Authors: Ted Way Tom Harper
As power demand accelerates, transmission upgrades, substations, transformers and other electrical infrastructure are playing a larger role in determining when new capacity can come online. Recent industry data shows that projects entering service in 2025 spent more than seven years on average moving from the grid-connection process to operation, with approximately four of those years occurring after an interconnection agreement was reached.1
Protecting the project schedule requires looking beyond construction of the data center itself to the infrastructure required to energize it.
The path to opening now extends beyond construction
For most of the industry's history, construction set the schedule. If the building was done, the power was usually ready too. That is no longer true.
Recent grid data illustrates the challenge. Projects that began operating in 2025 spent an average of more than three years reaching an interconnection agreement and approximately four additional years getting from approval to operation.1
The causes extend beyond the interconnection process itself. Among projects under construction or development, permitting accounted for 29% of milestone change requests and supply chain delays accounted for another 23%. Other causes included equipment availability, procurement, construction issues and land ownership.1
More capital is also at risk. Average global data center construction costs are forecast to reach approximately $11.3 million per MW in 2026, up from $7.7 million per MW in 2020.2
Long lead times increase the cost of delay
Delay in start-up insurance, or DSU, is designed to protect against certain financial losses when insured physical damage during construction delays project completion.
Typically arranged as an extension of contract works coverage, DSU may cover anticipated lost profit and certain additional and continuing expenses following a covered delay. Coverage depends on the specific terms, conditions and exclusions of the policy.
For data centers, one factor deserves particular attention: how long will it take to replace critical electrical equipment following a covered loss?
Increased lead times for large power transformers are important to account for when determining an appropriate DSU indemnity period. If a critical transformer is damaged during transit, installation, testing or commissioning, how long could it take to secure a suitable replacement, complete the associated work and recover the project schedule?
An indemnity period that doesn't reflect current replacement timelines could leave a project exposed to financial losses after the applicable coverage period ends.
Critical equipment carries risk at every stage
Understanding where critical equipment is located throughout the project lifecycle is critical.
Transformers, switchgear and other specialized equipment may spend considerable time in manufacturing, transit and temporary storage before installation. Testing and commissioning introduce additional exposures, and coverage amendments, before commercial operation begins.
Insurance planning should therefore consider not only the finished project but the entire journey of equipment critical to energization.
Owners and their advisors should examine how builder's risk, inland transit, marine cargo, off-site storage, testing and DSU provisions interact. A gap between these coverage parts becomes especially important when one damaged component has a replacement timeline measured in years rather than months. This reflects a broader principle for data center development: decisions made during construction can affect resilience, insurability and commercial performance long after completion.
Physical damage is only part of the delay exposure
Longer equipment lead times create one challenge for DSU. Delays without physical damage create another.
Traditional DSU coverage is only triggered when there's precipitating physical damage by an insured peril. Nonphysical causes, including certain regulatory, labor or political events, are commonly excluded.
A project could be delayed because required transmission infrastructure isn't ready, a substation or supporting infrastructure could encounter permitting delays or equipment shortages could affect the ability to complete required utility upgrades. None of those scenarios necessarily involve physical damage to the data center itself.
It's important to understand which events can be transferred through insurance, which are allocated through contracts and which, ultimately, remain on the balance sheet.
Pressure-test the path to commercial operation
1. Which infrastructure actually determines the commercial operation date?
2. Which equipment has the longest replacement timeline?
3. Is critical equipment protected throughout its journey?
4. What happens if the delay doesn't involve physical damage?
5. Do project values and expected revenues still reflect current conditions?
6. Are lenders and other stakeholders aligned on the risk?
Protect the path to commercial operation
Power infrastructure, equipment availability, permitting and other dependencies can ultimately determine when a facility begins generating revenue.
The goal is to understand what could delay commercial operation, which of those events can be transferred through insurance and how the remaining exposure should be managed through contracts, engineering, procurement and contingency planning. This requires bringing the conversations on construction, power, procurement, insurance and financing together earlier in the project lifecycle.
Gallagher's Data Center practice can help owners, developers, investors and lenders evaluate project dependencies, test DSU structures against realistic delay scenarios and build an insurance program around the facility's actual path to commercial operation.
Contact your Gallagher representative to discuss your data center construction and delay risks.