Authors: Ted Way Tom Harper

null

As power demand accelerates, transmission upgrades, substations, transformers and other electrical infrastructure are playing a larger role in determining when new capacity can come online. Recent industry data shows that projects entering service in 2025 spent more than seven years on average moving from the grid-connection process to operation, with approximately four of those years occurring after an interconnection agreement was reached.1

Protecting the project schedule requires looking beyond construction of the data center itself to the infrastructure required to energize it.

The path to opening now extends beyond construction

For most of the industry's history, construction set the schedule. If the building was done, the power was usually ready too. That is no longer true.

Recent grid data illustrates the challenge. Projects that began operating in 2025 spent an average of more than three years reaching an interconnection agreement and approximately four additional years getting from approval to operation.1

The causes extend beyond the interconnection process itself. Among projects under construction or development, permitting accounted for 29% of milestone change requests and supply chain delays accounted for another 23%. Other causes included equipment availability, procurement, construction issues and land ownership.1

More capital is also at risk. Average global data center construction costs are forecast to reach approximately $11.3 million per MW in 2026, up from $7.7 million per MW in 2020.2

Long lead times increase the cost of delay

Delay in start-up insurance, or DSU, is designed to protect against certain financial losses when insured physical damage during construction delays project completion.

Typically arranged as an extension of contract works coverage, DSU may cover anticipated lost profit and certain additional and continuing expenses following a covered delay. Coverage depends on the specific terms, conditions and exclusions of the policy.

For data centers, one factor deserves particular attention: how long will it take to replace critical electrical equipment following a covered loss?

Increased lead times for large power transformers are important to account for when determining an appropriate DSU indemnity period. If a critical transformer is damaged during transit, installation, testing or commissioning, how long could it take to secure a suitable replacement, complete the associated work and recover the project schedule?

An indemnity period that doesn't reflect current replacement timelines could leave a project exposed to financial losses after the applicable coverage period ends.

Critical equipment carries risk at every stage

Understanding where critical equipment is located throughout the project lifecycle is critical.

Transformers, switchgear and other specialized equipment may spend considerable time in manufacturing, transit and temporary storage before installation. Testing and commissioning introduce additional exposures, and coverage amendments, before commercial operation begins.

Insurance planning should therefore consider not only the finished project but the entire journey of equipment critical to energization.

Owners and their advisors should examine how builder's risk, inland transit, marine cargo, off-site storage, testing and DSU provisions interact. A gap between these coverage parts becomes especially important when one damaged component has a replacement timeline measured in years rather than months. This reflects a broader principle for data center development: decisions made during construction can affect resilience, insurability and commercial performance long after completion.

Physical damage is only part of the delay exposure

Longer equipment lead times create one challenge for DSU. Delays without physical damage create another.

Traditional DSU coverage is only triggered when there's precipitating physical damage by an insured peril. Nonphysical causes, including certain regulatory, labor or political events, are commonly excluded.

A project could be delayed because required transmission infrastructure isn't ready, a substation or supporting infrastructure could encounter permitting delays or equipment shortages could affect the ability to complete required utility upgrades. None of those scenarios necessarily involve physical damage to the data center itself.

It's important to understand which events can be transferred through insurance, which are allocated through contracts and which, ultimately, remain on the balance sheet.

Pressure-test the path to commercial operation

The time to evaluate delay risk is before procurement decisions, contracts and insurance structures are locked in. Early planning gives organizations more opportunity to align DSU coverage with the project's actual schedule and risk profile.

1. Which infrastructure actually determines the commercial operation date?

Map the complete path to energization, including the data center, transmission upgrades, substations, transformers, utility work and required permits. Identify dependencies outside the owner's direct control.

2. Which equipment has the longest replacement timeline?

Don't base the DSU indemnity period solely on the planned construction schedule. Consider how long it would take to replace critical equipment following a covered loss and what additional work would be needed before the project could resume.

3. Is critical equipment protected throughout its journey?

Review insurance for equipment during manufacturing, transit, off-site storage, installation, testing and commissioning. Consider where one policy ends and another begins.

4. What happens if the delay doesn't involve physical damage?

Model realistic scenarios involving interconnection, permitting, utility infrastructure and other dependencies. Determine which could trigger insurance and which may need to be addressed through contracts, contingency planning or risk retention.

5. Do project values and expected revenues still reflect current conditions?

Construction costs and equipment pricing can change during a multiyear build. Revisit insured values and projected income as the project evolves.

6. Are lenders and other stakeholders aligned on the risk?

A delayed commercial operation date can affect future revenue and financial obligations. Coverage structure, indemnity periods and project assumptions should be discussed early rather than waiting until financial close.

Protect the path to commercial operation

Power infrastructure, equipment availability, permitting and other dependencies can ultimately determine when a facility begins generating revenue.

The goal is to understand what could delay commercial operation, which of those events can be transferred through insurance and how the remaining exposure should be managed through contracts, engineering, procurement and contingency planning. This requires bringing the conversations on construction, power, procurement, insurance and financing together earlier in the project lifecycle.

Gallagher's Data Center practice can help owners, developers, investors and lenders evaluate project dependencies, test DSU structures against realistic delay scenarios and build an insurance program around the facility's actual path to commercial operation.

Contact your Gallagher representative to discuss your data center construction and delay risks.

Author Information


Disclaimer

The information contained herein is offered as insurance Industry guidance and provided as an overview of current market risks and available coverages and is intended for discussion purposes only. This publication is not intended to offer financial, tax, legal or client-specific insurance or risk management advice. General insurance descriptions contained herein do not include complete Insurance policy definitions, terms, and/or conditions, and should not be relied on for coverage interpretation. Actual insurance policies must always be consulted for full coverage details and analysis. Gallagher publications may contain links to non-Gallagher websites that are created and controlled by other organizations. We claim no responsibility for the content of any linked website, or any link contained therein. The inclusion of any link does not imply endorsement by Gallagher, as we have no responsibility for information referenced in material owned and controlled by other parties. Gallagher strongly encourages you to review any separate terms of use and privacy policies governing use of these third-party websites and resources. Insurance brokerage and related services provided by Arthur J. Gallagher Risk Management Services, LLC License Nos. IL 100292093 / CA 0D69293 and its US licensed retail brokerage affiliates.

© 2026 Arthur J. Gallagher & Co.