Author: Tom Harper
Developers have spent years securing customers for power and compute. The next critical counterparty may be the one willing to absorb the completed asset's physical and financial risk.
Over the past several years, the insurance market has evaluated digital infrastructure projects developing at a pace that often exceeds the availability of traditional loss data. Insurers have had to assess technologies and operating models that can evolve faster than historical experience.
Insurance underwriting typically draws on loss history, exposure data, engineering analysis and catastrophe modeling to estimate the frequency and severity of future claims. When an exposure is new or difficult to quantify, insurers may respond with tighter terms, higher pricing, larger deductibles, constrained limits or specialized placements.
AI infrastructure introduces several developing exposures. These include rising rack densities, direct-to-chip liquid cooling, coolant distribution near energized equipment, new electrical architectures, lithium-ion backup systems, modular construction, phased commissioning and rapidly changing generations of high-value compute equipment.
The greater test may come when today's projects leave construction-specific policies and enter permanent property programs. At that point, insurers are no longer assessing a project with a defined construction value and completion date. They are assessing the concentration of assets and income that will remain on the site year after year.
From construction project to property concentration
Construction insurance is designed around a project with a defined contract value, schedule and completion date. Permanent property insurance must address the completed accumulation: the building, power infrastructure, cooling systems, network equipment, high-value compute and the income that depends on those systems working together.
At a large AI campus, the equipment inside the facility may rival or exceed the value of the building itself. A single event could affect more than replacement cost. It could also disrupt contracted revenue, customer obligations, debt service and access to specialized equipment with long replacement times. The exposure is therefore shaped by both physical concentration and financial dependency.
Insurers must determine how much value they are prepared to support at one campus, within one catastrophe footprint, on one utility system and across their wider portfolios. The practical constraint may not be the insurance market's theoretical global capacity. It may be the amount of capacity available for a specific project at acceptable pricing, deductibles and terms.
The risk offtaker
Digital infrastructure developers are already familiar with offtake. They need to know who will purchase the power, lease the capacity or consume the compute. They also need confidence that those counterparties can support the project's economics and financing.
Permanent property insurance introduces another form of offtake: risk offtake.
In this context, the insurer is the risk offtaker. Through the permanent property program, insurers agree to assume a defined portion of the financial consequences associated with physical loss and resulting disruption.
That support isn't unlimited. A project may have strong customer demand and a long-term commercial contract, yet still present a challenging insurance proposition because of:
- The concentration of property and equipment at one location
- Exposure to natural catastrophes
- Shared cooling, electrical or utility dependencies
- Limited physical separation between critical systems
- The potential for one failure to affect multiple buildings or operating units
- Long replacement times for specialized equipment
A strong commercial offtaker doesn't automatically make a project an acceptable insurance risk.
Developers have often addressed insurance after site selection, power procurement and major design decisions. If permanent property capacity becomes more selective for highly concentrated AI infrastructure, the expectations of the risk offtaker may need to be considered alongside those of power, compute and capital providers.
Capital providers are looking beyond growth
Capital providers are examining how large AI infrastructure projects will perform under a range of demand, operating and financing conditions. Their questions may include the durability of demand, customer concentration, leverage, residual equipment value and the capital required to sustain continued expansion.
The AI infrastructure ecosystem can also be highly interconnected. A large technology company may act as a customer, investor, supplier, financing counterparty or strategic partner. Infrastructure operators may finance projects against equipment, customer contracts or projected cash flow. Suppliers may participate in customer financing.
This doesn't establish that the sector is a bubble or that these financing structures are unsound. It does, however, reinforce the difference between projected growth and financeable risk.
As capital becomes more selective, lenders and investors may place greater emphasis on whether insurance protects both the physical collateral and the cash flow supporting repayment.
When insurance becomes part of credit quality
The distinction between construction and permanent property insurance is likely to become most visible as a project approaches completion.
A lender may have accepted a construction policy while a facility was being built. The permanent insurance program must address a different exposure and may include different limits, deductibles, exclusions, valuation provisions and insurer requirements.
Capital providers may need to understand:
- Whether available property limits align with replacement cost, modeled losses and outstanding debt
- Whether business interruption protection reflects the project's revenue and debt-service obligations
- Whether participating insurers satisfy financing requirements
- Whether key equipment, utility dependencies and natural catastrophe exposures are adequately addressed
- Whether policy conditions align with the requirements in financing documents
Non-recourse, off-balance-sheet and rated financing structures may require additional precision.
If available insurance doesn't meet financing requirements, project stakeholders may need to consider larger deductibles, additional reserves, engineering improvements, revised loan terms or alternative sources of capital. These changes can affect the project's economics. Insurance then stops being a procurement line item and becomes part of the asset's credit quality.
Insurers want well-managed risks. Lenders want insurance that supports the financing. Developers need access to both capital and insurance capacity.
The underwriter may get a vote again
A more selective permanent property market could move insurance considerations further upstream.
Underwriters and risk engineers may want to understand design decisions involving:
- Fire compartmentation and physical separation
- Flood protection and roof resilience
- Transformer configuration and electrical redundancy
- Coolant-leak detection and water containment
- Lithium-ion battery protection
- Spare equipment and replacement strategies
- Testing and commissioning
- The ability to isolate a failure without disabling the wider campus
Engaging insurers and risk engineers early doesn't mean allowing insurance considerations to drive every design decision. It gives developers a clearer view of how design choices may affect available capacity, policy terms, deductibles and financing requirements.
A decision made to reduce costs or accelerate construction may be difficult or expensive to change once concrete has been poured and equipment has been energized.
The traditional question has been: "This is what we are building. What will it cost to insure?"
The more useful question may be: "If insurers and lenders are expected to support this asset for years, what needs to be considered in its design now?"
Questions to address before the design is fixed
- How much value will accumulate at the completed campus?
Consider the building, equipment, infrastructure and potential business interruption exposure rather than construction cost alone. - Which systems could create a common point of failure?
Evaluate whether a utility, electrical, cooling, fire-protection or control-system failure could affect multiple buildings or operating units. - What loss scenarios will influence insurer and lender requirements?
Compare replacement cost, modeled losses, proposed limits and financing obligations early enough to act on material gaps. - Are specialized equipment and critical components replaceable within the assumed recovery period?
Long lead times may affect both the physical-damage assessment and the required period of business interruption protection. - Do the proposed insurance terms align with financing documents?
Test limits, deductibles, insurer requirements and policy provisions before the project transitions from construction to permanent operations. - Which engineering improvements could strengthen operational resilience and insurability?
Some investments may reduce the likelihood or severity of a loss while preserving more insurance and financing options.
The next constraint
The growth of AI infrastructure may be entering a more disciplined phase in which site selection, engineering, insurance and finance can no longer operate as sequential workstreams.
A site may offer abundant power but present challenging catastrophe characteristics. A cooling design may support greater density while increasing the potential for a shared failure. A campus may work operationally but exceed the insurance capacity that individual insurers are prepared to deploy. A customer contract may support financing while increasing the business interruption exposure.
For the past several years, the defining question has been how quickly the industry can build. The next question may be whether completed concentrations of risk can be insured and financed on terms that preserve the project's economics.
Project stakeholders don't want to discover the answer at completion.
By considering risk offtake alongside power, compute and capital from the beginning, developers can better understand potential constraints, preserve more design and financing options and make informed decisions about the long-term resilience of the asset.
Gallagher can support early conversations among project stakeholders, risk engineers and insurance markets to help identify how design decisions, asset concentration and financing requirements may affect a project's permanent property strategy. Contact your Gallagher representative to discuss these considerations during site selection, design and financing.